View Rule

View EO 12866 Meetings Printer-Friendly Version     Download RIN Data in XML

NRC RIN: 3150-AJ49 Publication ID: Spring 2015 
Title: ●Mitigation Strategies for Beyond Design Basis Events [NRC-2014-0240]  
Abstract:

This rulemaking merges: 1) Station Blackout Mitigation Strategies (RIN 3150-AJ08), and 2) Strengthening and Integrating Onsite Emergency Response Capabilities (RIN 3150-AJ11).  The purpose of this rulemaking is to enhance mitigation strategies for nuclear power reactors for beyond-design-basis external events.  This rulemaking addresses recommendations from the Near Term Task Force (NTTF) related to station blackout, spent fuel pool long term cooling, and emergency preparedness (NTTF recommendations 4,7,8,and portions of 9, 10, and 11).  In SRM-SECY-11-0124, the Commission directed the staff to initiate the station blackout rulemaking as a high-priority activity.  Also, SRM-SECY-11-0137 approved the staff’s proposal to strengthen and integrate onsite emergency response capabilities such as emergency operating procedures (EOPs), severe accident management guidelines (SAMGs), and the extensive damage mitigation guidelines (EDMGs).  In SRM-SECY-14-0046, the Commission approved the consolidation of the rulemaking activities.  The rulemaking will make generically applicable the requirements in the Mitigation Strategies Order EA-12-049 and Spent Fuel Pool Instrumentation Order EA-12-051 from 2012.  This rulemaking will partially address PRM-50-96 for long-term cooling capabilities in the event of a solar storm. Additionally, this rule fully addresses PRMs 50-97, 50-98, 50-100, 50-101, and 50-102.

 

 
Agency: Nuclear Regulatory Commission(NRC)  Priority: Other Significant 
RIN Status: First time published in the Unified Agenda Agenda Stage of Rulemaking: Proposed Rule Stage 
Major: No  Unfunded Mandates: No 
CFR Citation: 10 CFR 50    10 CFR 52   
Legal Authority: 42 U.S.C. 2201    42 U.S.C. 5841   
Legal Deadline:  None
Timetable:
Action Date FR Cite
NPRM  12/00/2015 
Additional Information: The staff has briefed the Advisory Committee for Reactor Safeguards on several occasions, including the Regulatory Policies and Practices Subcommittee on December 5, 2012, and April 23, 2013 (concerning the station blackout mitigation strategies regulatory basis), the Plant Operation and Fire Protection Subcommittee on February 6, 2103 (concerning the onsite emergency response capabilities regulatory basis), the ACRS full committee on June 5, 2013 (concerning the station blackout mitigation strategies regulatory basis), and July 10, 2014 (concerning consolidation of the station blackout mitigation strategies and onsite emergency capabilities rulemakings). The proposed rulemaking package is due to the Commission April 30, 2015. Three draft regulatory guides will be issued with the proposed rule for comment. The final rule is on schedule to be provided to the Commission December 2016.
Regulatory Flexibility Analysis Required: No  Government Levels Affected: None 
Federalism: No 
Included in the Regulatory Plan: No 
RIN Data Printed in the FR: No 
Related RINs: Merged with 3150-AJ11, Merged with 3150-AJ08 
Agency Contact:
Timothy A. Reed
Nuclear Regulatory Commission
Office of Nuclear Reactor Regulation,
Washington, DC 20555-0001
Phone:301 415-1462
Email: timothy.reed@nrc.gov