View Rule
View EO 12866 Meetings | Printer-Friendly Version Download RIN Data in XML |
FERC | RIN: 1902-AF33 | Publication ID: Spring 2019 |
Title: Reform of Generator Interconnection Procedures and Agreements | |
Abstract:
The Commission granted in part and denied in part the requests for rehearing and clarification of its determination in Order No. 845, which amended the Commission’s pro forma Large Generator Interconnection Procedures and pro forma Large Generator Interconnection Agreement to improve certainty, promote more informed interconnection decisions, and enhance interconnection processes. The reforms were intended to ensure that the generator interconnection process is just and reasonable and not unduly discriminatory or preferential (Docket Nos. RM17-8-000 and RM17-8-001). |
|
Agency: Federal Energy Regulatory Commission(FERC) | Priority: Substantive, Nonsignificant |
RIN Status: Previously published in the Unified Agenda | Agenda Stage of Rulemaking: Final Rule Stage |
Major: No | Unfunded Mandates: No |
EO 13771 Designation: Independent agency | |
CFR Citation: 18 CFR 35 18 CFR 37 | |
Legal Authority: 16 U.S.C. 791a to 825r 16 U.S.C. 2601 to 2645 31 U.S.C. 9701 42 U.S.C. 7101 to 7352 |
Legal Deadline:
None |
|||||||||||||||||||||||||||||||||
Timetable:
|
Regulatory Flexibility Analysis Required: No | Government Levels Affected: None |
Included in the Regulatory Plan: No | |
RIN Data Printed in the FR: No | |
Agency Contact: Adam Pan Legal Information, Office of the General Counsel Federal Energy Regulatory Commission 888 First Street NE., Washington, DC 20426 Phone:202 502-6023 Email: adam.pan@ferc.gov Tony Dobbins Technical Information, Office of Energy Policy and Innovation Federal Energy Regulatory Commission 888 First Street NE., Washington, DC 20426 Phone:202 502-6630 Email: tony.dobbins@ferc.gov Kathleen Ratcliff Technical Information, Office of Energy Market Regulation Federal Energy Regulatory Commission 888 First Street NE., Washington, DC 20426 Phone:202 502-8018 Email: kathleen.ratcliff@ferc.gov |