DOD/COE | RIN: 0710-AB22 | Publication ID: Fall 2022 |
Title: Policy and Procedures for Processing Requests to Alter US Army Corps of Engineers Civil Works Projects Pursuant to 33 U.S.C. 408 | |
Abstract:
Where a party other than the US Army Corps of Engineers (Corps) seeks to use or alter a Civil Works project that the Corps constructed, the proposed use or alteration is subject to the prior approval of the Corps. Some examples of such alterations include an improvement to the project; relocation of part of the project; or installing utilities or other non-project features. This requirement was established in section 14 of the Rivers and Harbors Act of 1899 and is codified at 33 U.S.C. 408 (section 408). Section 408 provides that the Corps may grant permission for another party to alter a Civil Works project upon a determination that the alteration proposed will not be injurious to the public interest and will not impair the usefulness of the Civil Works project. The Corps is proposing to convert its policy that governs the section 408 program to a binding regulation. This policy, Engineer Circular 1165-2-220, Policy and Procedural Guidance for Processing Requests to Alter US Army Corps of Engineers Civil Works Projects Pursuant to 33 U.S.C. 408, was issued in September 2018. |
|
Agency: Department of Defense(DOD) | Priority: Other Significant |
RIN Status: Previously published in the Unified Agenda | Agenda Stage of Rulemaking: Proposed Rule Stage |
Major: No | Unfunded Mandates: No |
CFR Citation: 33 CFR 350 | |
Legal Authority: 33 U.S.C. 408 |
Legal Deadline:
None |
||||||
Statement of Need: Through the Civil Works program, the US Army Corps of Engineers (Corps), in partnership with stakeholders, has constructed many Civil Works projects across the Nation’s landscape. Given the widespread locations of these projects, there may be a need for others outside of the Corps to alter or occupy these projects and their associated lands. Reasons for alterations could include activities such as improvements to the project; relocation of part of the project; or installing utilities or other non-project features. In order to ensure that these projects continue to provide their intended benefits to the public, Congress provided that any use or alteration of a Civil Works project by another party is subject to the prior approval of the Corps. This requirement was established in section 14 of the Rivers and Harbors Act of 1899 and is codified at 33 U.S.C. 408 (section 408). Specifically, section 408 provides that the Corps may grant permission for another party to alter a Civil Works project upon a determination that the alteration proposed will not be injurious to the public interest and will not impair the usefulness of the Civil Works project. The Corps is proposing to convert its policy that governs the section 408 program to a binding regulation. Engineer Circular 1165-2-220, Policy and Procedural Guidance for Processing Requests to Alter US Army Corps of Engineers Civil Works Projects Pursuant to 33 U.S.C. 408 was issued in September 2018. |
||||||
Summary of the Legal Basis: The Corps has legal authority over the section 408 program under 33 U.S.C. 408. |
||||||
Alternatives: The preferred alternative would be to conduct rulemaking to issue the requirements governing the section 408 review process in the form of a binding regulation. The current Corps policy appears in an Engineer Circular that has expired. The next best alternative would involve issuing these requirements in the form of an Engineer Regulation. That alternative would not fulfill the intent of the law because it would not be binding on the regulated public. |
||||||
Anticipated Costs and Benefits: The proposed rule would reduce costs to the regulated public by clarifying the applicable requirements and providing consistent implementation of these requirements across the Corps program. It is anticipated that a form would be developed for submission of requests which would trigger the Paperwork Reduction Act compliance process and any associated costs will be evaluated at that time. |
||||||
Risks: The proposed action is not anticipated to increase risk to public health, safety, or the environment because it outlines the procedures the Corps will follow when evaluating requests for section 408 permissions. The Corps will comply with all statutory requirements when reviewing requests. |
||||||
Timetable:
|
Regulatory Flexibility Analysis Required: No | Government Levels Affected: None |
Small Entities Affected: No | Federalism: No |
Included in the Regulatory Plan: Yes | |
RIN Data Printed in the FR: No | |
Agency Contact: Virginia Rynk Department of Defense U.S. Army Corps of Engineers Attn: CECW-EC, 441 G Street NW, Washington, DC 20314 Phone:202 761-4741 |