Skip to main content
An official website of the United States government
The .gov means it's official.
Federal government websites often end in .gov or .mil. Before sharing sensitive information, make sure you're on a federal government site.
The site is secure.
The https:// ensures that you are connecting to the official website and that any information you provide is encrypted and transmitted securely.
Search:
Agenda
Reg Review
ICR
This script is used to control the display of information in this page.
Display additional information by clicking on the following:
All
Brief and OIRA conclusion
Abstract/Justification
Legal Statutes
Rulemaking
FR Notices/Comments
IC List
Burden
Misc.
Common Form Info.
Certification
View Information Collection (IC) List
View Supporting Statement and Other Documents
Please note that the OMB number and expiration date may not have been determined when this Information Collection Request and associated Information Collection forms were submitted to OMB. The approved OMB number and expiration date may be found by clicking on the Notice of Action link below.
View ICR - OIRA Conclusion
OMB Control No:
1219-0019
ICR Reference No:
201311-1219-001
Status:
Historical Active
Previous ICR Reference No:
201009-1219-003
Agency/Subagency:
DOL/MSHA
Agency Tracking No:
Title:
Slope and Shaft Sinking Plans, 30 CFR 77.1900 (Pertains to the surface work areas of underground coal mines)
Type of Information Collection:
Extension without change of a currently approved collection
Common Form ICR:
No
Type of Review Request:
Regular
OIRA Conclusion Action:
Approved without change
Conclusion Date:
03/25/2014
Retrieve Notice of Action (NOA)
Date Received in OIRA:
01/31/2014
Terms of Clearance:
Inventory as of this Action
Requested
Previously Approved
Expiration Date
03/31/2017
36 Months From Approved
03/31/2014
Responses
68
0
73
Time Burden (Hours)
1,360
0
1,460
Cost Burden (Dollars)
51
0
1,272
Abstract:
Section 103(h) of the Federal Mine Safety and Health Act of 1977 (Mine Act), 30 U.S.C. § 813, authorizes MSHA to collect information necessary to carry out its duty in protecting the safety and health of miners. Title 30 C.F.R. § 77.1900 requires underground coal mine operators to submit for approval a plan that will provide for the safety of workmen in each slope or shaft that is commenced or extended from the surface to the underground coal mine. Each slope or shaft sinking operation is unique in that each operator uses different methods and equipment and encounters different geological strata which make it impossible for a single set of regulations to ensure the safety of the miners under all circumstances. This makes an individual slope or shaft sinking plan necessary. The plan must be consistent with prudent engineering design. Plans include the name and location of the mine; name and address of the mine operator; a description of the construction work and methods to be used in construction of the slope or shaft, and whether all or part of the work will be performed by a contractor; the elevation, depth and dimensions of the slope or shaft; the location and elevation of the coalbed; the general characteristics of the strata through which the slope or shaft will be developed; the type of equipment which the operator proposes to use; the system of ventilation to be used; and safeguards for the prevention of caving during excavation.
Authorizing Statute(s):
PL:
Pub.L. 91 - 173 103(h)
Name of Law: Federal Mine Safety & Health Act of 1977
Citations for New Statutory Requirements:
None
Associated Rulemaking Information
RIN:
Stage of Rulemaking:
Federal Register Citation:
Date:
Not associated with rulemaking
Federal Register Notices & Comments
60-day Notice:
Federal Register Citation:
Citation Date:
78 FR 66071
11/04/2013
30-day Notice:
Federal Register Citation:
Citation Date:
79 FR 5457
01/31/2014
Did the Agency receive public comments on this ICR?
No
Number of Information Collection (IC) in this ICR:
1
IC Title
Form No.
Form Name
Slope and Shaft Sinking Plans
ICR Summary of Burden
Total Approved
Previously Approved
Change Due to New Statute
Change Due to Agency Discretion
Change Due to Adjustment in Estimate
Change Due to Potential Violation of the PRA
Annual Number of Responses
68
73
0
0
-5
0
Annual Time Burden (Hours)
1,360
1,460
0
0
-100
0
Annual Cost Burden (Dollars)
51
1,272
0
0
-1,221
0
Burden increases because of Program Change due to Agency Discretion:
No
Burden Increase Due to:
Burden decreases because of Program Change due to Agency Discretion:
No
Burden Reduction Due to:
Short Statement:
The burden hour decrease of 100 hours (from 1,460 hours to 1,360 hours) and the associated costs is due to fewer new underground coal mine openings, and as a result, a decreased number of shaft and slope projects. MSHA records show that there were less shafts and slopes under construction during the year 2012 than 2009. There was a decrease from 73 responses to 68 due to less plans in this adjustment and less respondents submitting plans (73 to 31 respondents/mines). The prior submission double counted revisions as responses from additional respondents. This submission more accurately notes that respondents submit multiple responses per respondent. There was also a cost burden decrease (from $1,272 to $51) resulting from a decrease in the number of shaft and slope plans submitted for facilities under construction and the increase in the number of plans sent to MSHA electronically.
Annual Cost to Federal Government:
$51,400
Does this IC contain surveys, censuses, or employ statistical methods?
No
Is the Supporting Statement intended to be a Privacy Impact Assessment required by the E-Government Act of 2002?
No
Is this ICR related to the Affordable Care Act [Pub. L. 111-148 & 111-152]?
No
Is this ICR related to the Dodd-Frank Wall Street Reform and Consumer Protection Act, [Pub. L. 111-203]?
No
Is this ICR related to the American Recovery and Reinvestment Act of 2009 (ARRA)?
No
Is this ICR related to the Pandemic Response?
Uncollected
Agency Contact:
Nicole Bouchet 202 646-2814 nicole.bouchet@dhs.gov
Common Form ICR:
No
On behalf of this Federal agency, I certify that the collection of information encompassed by this request complies with 5 CFR 1320.9 and the related provisions of 5 CFR 1320.8(b)(3).
The following is a summary of the topics, regarding the proposed collection of information, that the certification covers:
(a) It is necessary for the proper performance of agency functions;
(b) It avoids unnecessary duplication;
(c) It reduces burden on small entities;
(d) It uses plain, coherent, and unambiguous language that is understandable to respondents;
(e) Its implementation will be consistent and compatible with current reporting and recordkeeping practices;
(f) It indicates the retention periods for recordkeeping requirements;
(g) It informs respondents of the information called for under 5 CFR 1320.8 (b)(3) about:
(i) Why the information is being collected;
(ii) Use of information;
(iii) Burden estimate;
(iv) Nature of response (voluntary, required for a benefit, or mandatory);
(v) Nature and extent of confidentiality; and
(vi) Need to display currently valid OMB control number;
(h) It was developed by an office that has planned and allocated resources for the efficient and effective management and use of the information to be collected.
(i) It uses effective and efficient statistical survey methodology (if applicable); and
(j) It makes appropriate use of information technology.
If you are unable to certify compliance with any of these provisions, identify the item by leaving the box unchecked and explain the reason in the Supporting Statement.
Certification Date:
01/31/2014