View ICR - OIRA Conclusion



1902-0225 202201-1902-001
Historical Active 201908-1902-003
FERC FERC-725
FERC-725, Certification of Electric Reliability Organization; Procedures for Electric Reliability Standards
Extension without change of a currently approved collection   No
Regular
Approved with change 05/10/2022
Retrieve Notice of Action (NOA) 01/13/2022
In accordance with 5 CFR 1320, the information collection is approved. The previous terms of clearance still hold, which are: Any future FERC commission rules that require NERC to develop or modify NERC reliability standards will only be approved as part of this ICR by OMB if they are submitted as an ICR revision request with the required public notice and comment. In addition if such requests are connected to a rule-making that needs to be indicated as part of the ICR revision request.
  Inventory as of this Action Requested Previously Approved
05/31/2025 36 Months From Approved 05/31/2022
1,829 0 1,730
1,134,938 0 1,117,730
65,000 0 65,000