View Rule
| View EO 12866 Meetings | Printer-Friendly Version Download RIN Data in XML |
| DOE/ENDEP | RIN: 1901-AB77 | Publication ID: 2026 |
| Title: ●Emergency Interconnection of Electric Facilities and the Transfer of Electricity To Alleviate an Emergency Shortage of Electric Power | |
|
Abstract:
The Department of Energy (DOE) intends to update its rules concerning the emergency interconnection of electric facilities and the transfer of electricity to alleviate an emergency shortage of electric power pursuant to sections 202(c) and 202(d) of the Federal Power Act. Section 202(c) authorized the Federal Power Commission to order, upon application or on its own motion, a temporary connection of facilities and the generation, delivery, interchange, or transmission of electric energy necessary to alleviate an emergency shortage of electric power. Section 202(d) authorized an entity that is not otherwise subject to the jurisdiction of the Commission to establish temporary emergency connections without thereby becoming subject to the jurisdiction of the Commission and, upon approval by the Commission, to construct, under the same conditions, a permanent connection that would be only for emergency use. The Department of Energy Organization Act transferred the responsibilities under sections 202(c) and 202(d) of the Federal Power Act to the Secretary of Energy. A final rulemaking was promulgated on August 6, 1981 (46 FR 39984), establishing 10 CFR Part 205, sections 370 et seq. Since its original promulgation, the rule has not been substantively amended.
|
|
| Agency: Department of Energy(DOE) | Priority: Substantive, Nonsignificant |
| RIN Status: First time published in the Unified Agenda | Agenda Stage of Rulemaking: Proposed Rule Stage |
| Major: No | Unfunded Mandates: Undetermined |
| EO 14192 Designation: Deregulatory | |
| CFR Citation: 10 CFR 205.370-379 | |
| Legal Authority: 16 USC 824a(c) | |
|
Legal Deadline:
None |
||||||
Timetable:
|
| Regulatory Flexibility Analysis Required: Undetermined | Government Levels Affected: Federal, Local, State, Tribal |
| Federalism: Undetermined | |
| Included in the Regulatory Plan: No | |
| RIN Data Printed in the FR: No | |
|
Agency Contact: Alexander Fitzsimmons Director, Office of Cybersecurity, Energy Security, and Emergency Response Department of Energy Departmental and Others U.S. Department of Energy, 1000 Independence Ave SW, Washington, DC 20585 Phone:202 586-9044 Email: alexander.fitzsimmons@hq.doe.gov |
|