Title: Federal Acquisition Regulation (FAR); FAR Case 2012-028; Contractor Comment Period--Past Performance Evaluations 
Abstract:

DoD, GSA, and NASA issued a final rule to revise the Federal Acquisition Regulation to implement section 853 of the National Defense Authorization Act (NDAA) for Fiscal Year (FY) 2013 (Pub. L. 112-239, enacted January 2, 2013) and section 806 of the NDAA for FY 2012 (Pub. L. 112-81, enacted December 31, 2011, 10 U.S.C. 2302 Note). Section 853, entitled "Inclusion of Data on Contractor Performance in Past Performance Databases for Executive Agency Source Selection Decisions," and section 806, entitled "Inclusion of Data on Contractor Performance in Past Performance Databases for Source Selection Decisions," require revisions to the acquisition regulations on past performance evaluations so that contractors are provided "up to 14 calendar days… … from the date of delivery" of past performance evaluations "to submit comments, rebuttals, or additional information pertaining to past performance" for inclusion in the database. In addition, paragraph (c) of both sections 853 and 806 requires that agency evaluations of contractor performance, including any information submitted by contractors, be "included in the relevant past performance database not later than the date that is 14 days after the date of delivery of the information" (section 853(c)) to the contractor. The Governmentwide application of the statute will ensure that the Government has current performance information about contractors to help source selection officials make better award decisions. This case is included in the FAR retrospective review of existing regulations under Executive Order 13563. Additional information is located in the FAR final plan (2014), available at: https://www.acquisition.gov/.

 
Agency: DOD/GSA/NASA (FAR)(FAR)  Priority: Other Significant 
RIN Status: Previously published in the Unified Agenda Agenda Stage of Rulemaking: Completed Actions 
Major: No  Unfunded Mandates: No 
CFR Citation: 48 CFR 42   
Legal Authority: 40 USC 121(c)    10 USC ch 137    51 USC 20113   
Legal Deadline:  None
Timetable:
Action Date FR Cite
NPRM  08/07/2013  78 FR 48123   
NPRM Comment Period End  10/07/2013 
Final Rule  05/30/2014  79 FR 31197   
Final Rule Effective  07/01/2014 
Regulatory Flexibility Analysis Required: Yes  Government Levels Affected: Federal 
Small Entities Affected: Businesses  Federalism: No 
Included in the Regulatory Plan: No 
RIN Information URL: www.regulations.gov   Public Comment URL: www.regulations.gov  
RIN Data Printed in the FR: Yes 
Agency Contact:
Curtis E. Glover Sr.
Procurement Analyst
DOD/GSA/NASA (FAR)
1800 F Street, NW,
Washington, DC 20405
Phone:202 295-7548
Email: curtis.glover@gsa.gov