View Rule
View EO 12866 Meetings | Printer-Friendly Version Download RIN Data in XML |
NRC | RIN: 3150-AH29 | Publication ID: Spring 2015 |
Title: Risk-Informed Changes to Loss-of-Coolant Accident Technical Requirements [NRC-2004-0006] | |
Abstract:
This rulemaking would amend Part 50 to allow for a risk-informed alternative to the present maximum loss-of-coolant accident break size. This rulemaking would address a petition for rulemaking submitted by the Nuclear Energy Institute (PRM-50-75). The rulemaking is on hold pending action on the risk management regulatory framework initiative. Previously titled "Part 50.46a ECCS - Redefinition." . |
|
Agency: Nuclear Regulatory Commission(NRC) | Priority: Other Significant |
RIN Status: Previously published in the Unified Agenda | Agenda Stage of Rulemaking: Long-Term Actions |
Major: No | Unfunded Mandates: No |
CFR Citation: 10 CFR 50 10 CFR 52 | |
Legal Authority: 42 U.S.C. 2201 42 U.S.C. 5841 |
Legal Deadline:
None |
||||||||||||||||||||||||||||||
Timetable:
|
Additional Information: The NRC staff provided an initial draft final rule to the Advisory Committee on Reactor Safeguards (ACRS) on October 16, 2006. After reviewing the draft rule, the ACRS informed the Commission of numerous technical and policy concerns and recommended that the rule not be issued. The staff prepared a Commission paper (SECY-07-0082; May 16, 2007) to inform the Commission of the impact of the ACRS recommendations and to request guidance before proceeding with the rule. The Commission provided its guidance in a Staff Requirements Memorandum on August 10, 2007. On April 1, 2008, the staff provided an updated rule schedule to the Commission. In a meeting on August 6, 2008, selected NRC managers approved the staff's recommended resolution of the open issues related to the final rule. The staff prepared draft rule language incorporating the new positions into the rule and adding additional requirements for defense-in depth for pipe breaks larger than the transition break size. The OGC reviewed the revised rule language and recommended that portions of the rule be re-noticed to provide an opportunity for public comments on some of the new rule requirements. In a meeting on October 8, 2008, NRC managers decided to re-propose the entire rule. On December 18, 2008, the EDO signed a memorandum informing the Commission that the staff will re-notice the section 50.46a rule for additional public comments in August 2009. The staff discussed the revised proposed rule with the ACRS on May 6-7, 2009, and then published the rule on August 10, 2009 (74 FR 40006). On September 24, 2009, in response to a request from NEI, the NRC extended the public comment period by 120 days to close on January 22, 2010 (74 FR 48667). The NRC evaluated the public comments and prepared draft final rule language, which was posted on Regulations.gov on May 12, 2010. A public meeting was held on June 4, 2010, to discuss resolution of public comments and the draft rule language. The staff discussed the rule with the ACRS in September and October of 2010. In its letter of October 20, 2010, the ACRS concluded that the rule was an acceptable alternative for operating reactors. The final rule was provided to the Commission on December 10, 2010 (SECY-10-0161). Because of the evaluation of Fukushima Near-Term Task Force (NTTF) Recommendation 1 regarding the development of a new risk-informed regulatory framework and the Risk Management Task Force's report, "A Proposed Risk Management Regulatory Framework," the NRC staff requested that the Commission defer its decision on the draft final rule (SECY-10-0161) so that it could be reviewed and resubmitted later after the staff has completed its regulatory framework evaluation and has received regulatory framework direction from the Commission. However, the Commission's May 19. 2014, Staff Requirements Memorandum on NTTF Recommendation 1 deferred making regulatory framework decisions until after receipt of the staff's recommendations for a Risk-Management Regulatory Framework. After the staff determines its recommended Risk-Management Regulatory Framework approach and has received definitive regulatory framework direction from the Commission, the staff will re-evaluate the draft final section 50.46a rule to ensure its compatibility with the Commission's direction. When the staff determines that the rule is consistent with the Commission's direction, it will resubmit the draft final section 50.46a rule for Commission consideration. | |
Regulatory Flexibility Analysis Required: No | Government Levels Affected: None |
Small Entities Affected: No | Federalism: No |
Included in the Regulatory Plan: No | |
RIN Data Printed in the FR: No | |
Agency Contact: Richard F. Dudley Nuclear Regulatory Commission Office of Nuclear Reactor Regulation, Washington, DC 20555-0001 Phone:301 415-1116 Email: richard.dudley@nrc.gov |